MIP Construction of Gatehouse& Gate, Fencing

Comprehensive project information, milestones, progress, and documents

Completed FY 20-21 ID: 1072

MIP Construction of Gatehouse& Gate, Fencing

Primary Security Infrastructure

Location

Gatanga

Kakuzi/Mitubiri (Gatanga)

Sector(s)

Trade

Overall Completion

100%

Citizen Feedback

Share your thoughts or report issues about this project.

No feedback yet. Be the first to share!

Approved Cost

KSh 3,000,170

Est: KSh 3,000,000

Disbursed

KSh 3,000,170

100.0% of approved

Expenditure

KSh 0

Balance

KSh N/A

Project Information

Goal / Objective

Custom-Controlled Environment essential because the park functions as both a Special Economic Zone (SEZ) and an Export Processing Zone (EPZ).

Expected Output

The park is a legally bonded zone that will increase job creating and increase manufacturing knowledge

Project Code

4016

Implementation Details

Department

Trade, Industry, Tourism, Agriculture, Livestock and Fisheries

Implementing Agency

Trade, Industry, Tourism and Co-operatives

Funding Source

MCG

Still in Budget?

No

Project Timeline

Approval Date

June 01, 2024

Start Date

September 01, 2024

Expected Completion

June 01, 2025

Actual Completion

June 01, 2025

Project Milestones 0 milestones

No milestones defined for this project.

Project Documents 0 documents

No documents uploaded for this project.

Screening & Compliance

Climate & Disaster Risk

Not Done

ESHSG

Not Done

Technical & Financial Viability

Not Done

Quick Facts

Project ID
#1072
Status
Completed
Funds Available
KSh 3000170
Created
Nov 03, 2026
Last Updated
Nov 03, 2026

Statistics

Budget Utilization

100%

Physical Progress

100%