Kangema Hospital facelift

Comprehensive project information, milestones, progress, and documents

Completed FY 21-22 ID: 315

Kangema Hospital facelift

Facelift of Kangema Hospital

Location

KANGEMA

MUGURU (KANGEMA)

Sector(s)

HEALTH

Overall Completion

100%

Citizen Feedback

Share your thoughts or report issues about this project.

No feedback yet. Be the first to share!

Approved Cost

KSh N/A

Est: KSh 10,000,000

Disbursed

KSh 0

Expenditure

KSh 0

Balance

KSh N/A

Project Information

Goal / Objective

Renovation of Kangema Hospital

Project Code

Dev

Budget Item

Renovation of Kangema Hospital

Implementation Details

Department

Health and Sanitation

Implementing Agency

Not specified

Funding Source

MCG

Still in Budget?

No

Project Timeline

Approval Date

September 09, 2022

Start Date

November 10, 2022

Expected Completion

April 13, 2023

Actual Completion

December 12, 2022

Project Milestones 0 milestones

No milestones defined for this project.

Project Documents 0 documents

No documents uploaded for this project.

Screening & Compliance

Climate & Disaster Risk

Completed

ESHSG

Completed

Technical & Financial Viability

Completed

Quick Facts

Project ID
#315
Status
Completed
Created
Mar 10, 2026
Last Updated
Mar 10, 2026

Statistics

Budget Utilization

0%

Physical Progress

100%