Rehabilitation of Mumbu Borehole in Kahumbu
Comprehensive project information, milestones, progress, and documents
Last Updated
November 2026
Rehabilitation of Mumbu Borehole in Kahumbu
Installation of solar power system
Location
Kigumo
Kahumbu (Kigumo)
Sector(s)
Irrigation
Overall Completion
Citizen Feedback
Share your thoughts or report issues about this project.
Approved Cost
KSh 2,100,000
Est: KSh 2,100,000
Disbursed
KSh 2,100,000
100.0% of approved
Expenditure
KSh 0
Balance
KSh N/A
Project Information
Goal / Objective
To supply water to Mumbu community using clean energy
Expected Output
Functional borehole
Project Code
Dev.
Budget Item
Water
Implementation Details
Department
Environment, Natural Resources, Water and Irrigation
Implementing Agency
Environment
Funding Source
MCG
Project Timeline
Approval Date
July 15, 2024
Start Date
September 15, 2024
Expected Completion
June 30, 2025
Actual Completion
June 30, 2026
Project Milestones 0 milestones
No milestones defined for this project.
Project Documents 0 documents
No documents uploaded for this project.
Screening & Compliance
Climate & Disaster Risk
CompletedMitigation Actions:
Continous maintenance for sustainability
ESHSG
CompletedMitigation Actions:
Ensuring that Water is accessed by all community members
Technical & Financial Viability
CompletedDetails:
Conitinous maintenanace for sustainablity
Additional Remarks
Project is operational
Quick Facts
- Project ID
- #317
- Status
- Completed
- Funds Available
- KSh 2100000
- Created
- Nov 03, 2026
- Last Updated
- Nov 03, 2026
Related Projects
Statistics
Budget Utilization
Physical Progress