renovation of Mianyani ECDE centre- Ithanga Ward
Comprehensive project information, milestones, progress, and documents
Last Updated
April 2026
renovation of Mianyani ECDE centre- Ithanga Ward
renovation of Mianyani ECDE centre- Ithanga Ward
Location
GATANGA
ITHANGA (GATANGA)
Sector(s)
EDUCATION
Overall Completion
Citizen Feedback
Share your thoughts or report issues about this project.
Approved Cost
KSh 1,709,740
Est: KSh 1,709,740
Disbursed
KSh 1,709,740
100.0% of approved
Expenditure
KSh 1709740
Balance
KSh N/A
Project Information
Goal / Objective
provide learners with conducive learning enviroment .
Expected Output
no. of classrooms done
Budget Item
Development
Implementation Details
Department
Infrastructure, Roads, Housing and Transport
Implementing Agency
Not specified
Funding Source
MCG
Still in Budget?
No
Project Timeline
Approval Date
March 27, 2025
Actual Completion
March 27, 2025
Project Milestones 0 milestones
No milestones defined for this project.
Project Documents 0 documents
No documents uploaded for this project.
Screening & Compliance
Climate & Disaster Risk
Not DoneESHSG
Not DoneTechnical & Financial Viability
Not DoneQuick Facts
- Project ID
- #624
- Status
- Completed
- Created
- Mar 10, 2026
- Last Updated
- Mar 10, 2026
Related Projects
Statistics
Budget Utilization
Physical Progress