construction of 2no. ECDE classrooms at Githiga-Ruchu Ward.

Comprehensive project information, milestones, progress, and documents

Completed FY 23-24 ID: 653

construction of 2no. ECDE classrooms at Githiga-Ruchu Ward.

construction of 2no. ECDE classrooms at Githiga

Location

Kandara

Ruchu (Kandara)

Sector(s)

Education

Overall Completion

100%

Citizen Feedback

Share your thoughts or report issues about this project.

No feedback yet. Be the first to share!

Approved Cost

KSh 2,807,820

Est: KSh 2,807,820

Disbursed

KSh 2,807,820

100.0% of approved

Expenditure

KSh 2807820

Balance

KSh 0

Project Information

Goal / Objective

Provide learners with conducive learning environment

Expected Output

No. of classrooms done

Project Code

499

Budget Item

Development

Implementation Details

Department

Roads, Housing & Infrastructure

Implementing Agency

Roads & Infrastructure

Funding Source

MCG

Still in Budget?

No

Project Timeline

Approval Date

November 01, 2023

Expected Completion

February 16, 2024

Actual Completion

February 16, 2024

Project Milestones 0 milestones

No milestones defined for this project.

Project Documents 0 documents

No documents uploaded for this project.

Screening & Compliance

Climate & Disaster Risk

Not Done

Mitigation Actions:

YES

ESHSG

Not Done

Mitigation Actions:

YES

Technical & Financial Viability

Not Done

Quick Facts

Project ID
#653
Status
Completed
Created
Nov 03, 2026
Last Updated
Nov 03, 2026

Funding Breakdown

County Government

KSh 2807820

Total

KSh 2807820

Statistics

Budget Utilization

100%

Physical Progress

100%