Renovation of Gituto Mumbi & Kirogo ECDE Center

Comprehensive project information, milestones, progress, and documents

Completed FY 23-24 ID: 838

Renovation of Gituto Mumbi & Kirogo ECDE Center

Renovation of Gituto Mumbi & Kirogo ECDE Center

Location

KIHARU

WANGU (KIHARU)

Sector(s)

EDUCATION

Overall Completion

100%

Citizen Feedback

Share your thoughts or report issues about this project.

No feedback yet. Be the first to share!

Approved Cost

KSh 4,064,765

Est: KSh 4,064,765

Disbursed

KSh 4,064,765

100.0% of approved

Expenditure

KSh 0

Balance

KSh 0

Project Information

Goal / Objective

Provide learners with conducive learning environment

Expected Output

No. of classrooms done

Implementation Details

Department

Infrastructure, Roads, Housing and Transport

Implementing Agency

Not specified

Funding Source

MCG

Still in Budget?

No

Project Timeline

Approval Date

June 28, 2024

Actual Completion

June 28, 2024

Project Milestones 0 milestones

No milestones defined for this project.

Project Documents 0 documents

No documents uploaded for this project.

Screening & Compliance

Climate & Disaster Risk

Not Done

ESHSG

Not Done

Technical & Financial Viability

Not Done

Quick Facts

Project ID
#838
Status
Completed
Created
Mar 10, 2026
Last Updated
Mar 10, 2026

Statistics

Budget Utilization

100%

Physical Progress

100%