construction of rutune primary ECDE & renovation of kimathi primaryECDE – gaturi ward
Comprehensive project information, milestones, progress, and documents
Last Updated
March 2026
construction of rutune primary ECDE & renovation of kimathi primaryECDE – gaturi ward
Proposed construction of rutune primary e.c.d.e & renovation of kimathi primary e.c.d.e – gaturi ward
Location
KIHARU
GATURI (KIHARU)
Sector(s)
EDUCATION
Overall Completion
Citizen Feedback
Share your thoughts or report issues about this project.
Approved Cost
KSh 2,774,450
Est: KSh 2,774,450
Disbursed
KSh 2,774,450
100.0% of approved
Expenditure
KSh 2432870
Balance
KSh N/A
Project Information
Goal / Objective
Provide learners with conducive learning environment
Expected Output
No. of classrooms done
Implementation Details
Department
Infrastructure, Roads, Housing and Transport
Implementing Agency
Not specified
Funding Source
MCG
Still in Budget?
No
Project Timeline
Project Milestones 0 milestones
No milestones defined for this project.
Project Documents 0 documents
No documents uploaded for this project.
Screening & Compliance
Climate & Disaster Risk
Not DoneESHSG
Not DoneTechnical & Financial Viability
Not DoneQuick Facts
- Project ID
- #946
- Status
- Completed
- Created
- Mar 10, 2026
- Last Updated
- Mar 10, 2026
Related Projects
Statistics
Budget Utilization
Physical Progress